KEEP EJECTORS ONLINE
The performance of steam-jet ejectors can
be maintained by following these guidelines
 |
| Figure 1. In total, this illustration represents a
four-stage ejector system with two surface-contact intercondensers. A simple
single-stage system would comprise only the section in the outlined box. In
either case, motive force is provided by steam jets, which draw vapor from a
vessel and through the system. The condensers act to reduce the load on the
next ejector. |
Steam jet ejectors offer a simple, reliable means of producing vacuum, and
have a low installed cost as well. They are commonly found in process plants
having available steam. The vacuum produced is useful for many processes,
including evaporation, cooling, hydration, crystallization, deaeration and
filtration.
Through the simplicity of its construction (Figure 1), the steam-jet ejector
provides many years of troublefree operation. When a problem does occur,
many plant personnel do not have the experience to effectively troubleshoot an
ejector system, and precious production time is lost.
For example, a loss of vacuum in a multistage ejector system might have many
plant personnel disassembling the first-stage ejector booster, on the assumption
that one must check a unit from inlet to outlet. In fact (as will be shown later
in this article), this is the last place to look. Fortunately, downtime can be
kept to a minimum when a logical sequence of steps -- a checklist -- is followed
to locate the source of trouble.
Ejector basics
Ejectors can be classified as single-stage or multistage.
Multistage ejectors may be further divided into condensing or noncondensing
types. The single-stage ejector, the simplest and most common type, is generally
recommended for pressures ranging from atmospheric pressure (30 in. Hg absolute)
to 3 in. Hg abs. Discharge is typically at or near atmospheric pressure. The
boxed section of Figure 1 shows a single-stage system. The effects of injected
steam on process vapors is shown in figure 4. Multistage noncondensing ejectors
(MNEs) are used to produce suction pressures lower than 3 or 4 in. Hg abs. Steam
consumption in an MNE is relatively high. Each successive stage is required to
handle the load plus the motive steam from the previous stage. MNEs are
frequently used when low first cost is more important than long-range economy.
They are also used for intermittent service or when condensing water is not
available. MNEs are usually two-stage, although six-stage units have been used
successfully.
Multistage condensing ejectors (MCEs) are available in two through six
stages. Intercondensers (surface or direct-contact) between stages condense
steam from the preceding stage, reducing the load to be compressed in the
succeeding stage. A multistage system is shown in Figure 1.
Four-, five- and six-stage ejectors are used to achieve suction pressures as
low as 5 µm Hg abs. Under such vacuum conditions, pressure between the
preliminary stages is too low to permit condensation of ejector steam, and only
the final two stages are fitted with condensers. MCEs remove condensable vapor
ahead of a given ejector stage. They also permit use of a smaller ejector, and a
reduction in the amount of steam required. Condenser nomenclature is determined
by the corresponding operating conditions and functions.
Precondensers are used when the absolute pressure of the process is
sufficiently high to allow condensation at the temperature of the available
water supply. Noncondensables are removed from the precondenser by one or more
ejector stages. Condensers or inter-condensers liquefy process vapor and
motive steam from one or more preceding booster ejectors. Aftercondensers
condense steam discharging from the last-stage ejector, generally at
atmospheric pressures.
There are two basic types of condensers -- direct-contact and
surface-contact. In direct-contact (countercurrent, barometric design)
condensers, cooling water is mixed directly with the vapor to be condensed, then
discharged to atmosphere through a barometric leg or tailpipe of sufficient
length to overcome the atmospheric pressure. A means of cleaning up or otherwise
disposing the water that has become contaminated by process material is often
required. The surface-contact condenser permits main-condenser cooling water to
be used as cooling water through inter- and aftercondensers, for energy and
process-water conservation.
Where to start
When a vacuum problem arises there are several preliminary checks that
should be made on an ejector system before components are disassembled. First,
is the system design data readily available? Most ejector systems are
custom-designed to operate at a specified vacuum, given process loads, minimum
available steam pressure, maximum steam temperature, maximum discharge pressure
and maximum water temperature. It is impossible to evaluate the complete system
unless the manufacturer's design parameters are known.
A data sheet can be obtained from the manufacturer of the ejector system and
should list the design vacuum, capacity, interstage ejector vacuums, motive
steam pressure and temperature, condenser water-inlet and -outlet temperatures,
and discharge pressure. Critical dimensions such as the diameters of the ejector
nozzle orifice and the diffuser bore should also be know.
Once the design data are located, there is an ordered series of steps to
take in isolating ejector problems. One should check:
- Gauges
- Steam
- Water
- Process loads
- Field report and process logs
Pay attention to
instruments
When troubleshooting the ejector system, accurate pressure and temperature
measurements are needed to quickly locate the source of the problem. Therefore,
a check of the system's instrumentation is a necessity. All vacuum, pressure,
and temperature gages should be calibrated or replaced. A malfunctioning vacuum
gage may be found to be the entire vacuum "problem."
If the vacuum gage is several feet or more from the ejector system, check
the line running from the system to the gage for air leakage. It would take a
very small amount of air leakage in an instrument vacuum line to throw off the
measurement. If leakage is suspected, connect the test gage directly to the
ejector and compare vacuum measurements. If there is a valve in the vacuum line,
close it and observe the vacuum line, close it and observe the vacuum gage. If
it slowly loses vacuum, air leakage is occurring.
For troubleshooting purposes, overall, an absolute pressure gage is
preferred over a common vacuum gage. A common vacuum gage that reads in units of
inches of mercury vacuum is food for rough measurements by operators, but this
gage does not five the accuracy needed for a system analysis. Besides relative
inaccuracy, vacuum gages require a barometric pressure measurement to determine
an ejector's vacuum in units of inches of mercury absolute. There are a variety
of suppliers of such absolute-pressure gages.
 |
Figure 2. Steam-jet ejectors often provide a
compact means of delivering vacuum. |
Typically, an absolute mercury manometer is used for measuring the vacuum in
the Y and Z stages (Figure 2). It can be flooded with water and still give a
relatively accurate reading.
Replacement mercury U-tubes are also inexpensive, and are available from
various suppliers. Mercury-free units are also available, and are typically used
for the higher-vacuum ejectors such as W or X stages. There are also many
manufacturers of electronic vacuum gages that offer very accurate and portable
instruments. The gages are well worth the investment and should be kept in stock
only to be used when troubleshooting ejector systems.
Steam-pressure gages should be located on the steam chest of the ejectors or
as close to the unit as possible. It is important to know the actual operating
steam pressure since an ejector of critical-flow design (suction pressure less
than half discharge pressure) will not operate properly when even a few psi
below its design motive pressure. Compound steam pressure gages are recommended
since they will not be damaged when exposed to vacuum.
Steam
Motive steam plays probably the most important role in the operation of a
steam jet ejector. Since internal dimensions are fixed, the ejector is designed
for only one steam condition. When the steam condition changes there will be a
change in the operation and efficiency of the ejector.
In a critical-flow ejector a decrease in steam pressure of just a few psi
will result in a broken or unstable vacuum. An increase in steam pressure above
design will not have a noticeable effect in the operation of an ejector unless
the increase is significant (>25%).
Besides wasting steam, excess motive pressure tends to choke the venturi
with steam, thereby decreasing the suction capacity of the ejector. Note too
that the performance of ejectors designed for saturated steam will be adversely
affected if operated with super-heated steam.
The specific volume of steam increases with increasing temperature, which
may require an increase in pressure to maintain required steam flow. Otherwise,
as in the case of low steam pressure, the manufacturer must be consulted for a
redesign of the ejectors.
Excess moisture in steam is one of the most common problems found in
ejectors. Wet steam causes poor performance and, depending on the degree of
wetness, can permanently damage an ejector in a very short period of time. A
steam quality of less than 2% moisture is tolerable with most moderate vacuum
systems. However, ejectors designed for a vacuum of 5 mm Hg abs or less should
have steam that is completely dry or with a few degrees of superheat.
A telltale sign of wet steam is a fluttering needle on a steam pressure gage
during operation. But the only sure way to determine quality of steam is to test
it with a throttling calorimeter. This is a constant-enthalpy device that
measures steam pressure and temperature. When used in combination with a Mollier
chart, a reading of steam quality is obtained.
If steam is found to be wet, a steam separator should be installed in the
steam line as close to the ejector as possible. Keeping all steam piping, and
the steam separator, completely insulated will also help prevent the formation
of wet steam.
Figure 3. Largescale ejector systems are used
for vacuum chilling or steam recompression.
Water
Multiple-stage ejector systems will normally include condensers between
some or all stages. Condenser designs are based on maximum water temperature and
available flow. When inlet water temperature increases above design maximum,
loads to the following stage increase, resulting in a poorer vacuum at that
stage. If the affected stage is the last (Z) stage, then the vacuums of all the
preceding stages could also be affected.
The water temperature rise across a surface-contact condenser should be
compared with design. A temperature rise larger or smaller than design could be
an indication of a flow problem or fouling.
In direct-contact condensers, high or low water flowrates can cause problems
in the vacuum system. High water flow could flood the condenser, increasing
pressure drop, and therefore, the back pressure on the stage discharging into
it. Low water flow may not be distributed properly, allowing condensable load to
bypass into the following ejector and resulting in a poor vacuum.
 |
|
| Figure 4. The three basic
parts of an ejector are the nozzle, mixing chamber and diffuser. High-pressure
motive fluid passes through the nozzle, expands in the mixing chamber (where
pressure is converted to fluid velocity), and passes through the venturi throat
of the diffuser. Process fluid enters the suction port and is drawn into the
mixing chamber. The curves show the changes in velocity (above) and pressure
(below) of the motive fluid (blue) and Process fluid (magenta). |
|
 |
Process loads
A change in process load will have a direct effect on the ejector system.
Ejectors operate over a unique capacity curve, and any increase in load will
result in a higher absolute pressure. An increase in noncondensables will travel
through the system, affecting the following ejector stages. Discharge pressures
of each stage will increase to the point of a breakdown in operation. As in the
case of a changed steam condition, a change in process load will require
redesign by the manufacturer, if design vacuum is to be maintained.
Check the logs
Manufacturers' field service reports or process logs may offer clues to
present operational problems. the symptoms of a vacuum problem may be similar to
a past problem outlined, with solutions, in a service report. Process logs may
also indicate problems with steam pressure or changes in process conditions that
will have a direct effect on the vacuum system.
Now look at the
process
If the preliminary checklist is completed with no obvious problems found,
the next step is to determine whether the problem lies in the ejector system or
the process. The steps remaining to be considered are: no-load vacuum test
(single- or multistage) and an internal inspection.
The best way to determine if the vacuum problem lies in the ejector system
or the process is to isolate and test the ejector separate from the process. The
standard method of testing an ejector is to attach a blank, or blind flange, on
the suction flange of the ejector and measure the vacuum at no-load conditions.
A stable no-load vacuum is more difficult for an ejector to reach than a point
under load conditions, simply because there is a greater suction-to-discharge
pressure differential.
If the no-load vacuum measures the same as the manufacturer's test, then it
is reasonably safe to assume that the ejector is working at its design load
point. The problem may lie upstream from the suction of the ejector- possibly an
increase in air leakage or process load. It should be noted that unless
specified, an ejector may not have a stable vacuum at no-load even though it
works at its design load.
Figure 5. This gage, known as a piccolo, has calibrated
orifices to check vacuum quality.
To test an ejector at its design load point involves metering the design
load into the suction of the ejector. Use a calibrated orifice or a series of
orifices (such as can be found on an instrument known as a piccolo -- Figure 5),
and then compare the measured vacuum to the design vacuum. A curve can be
plotted and compared with the manufacturer's. This procedure should be
considered only after all other tests are exhausted. (The manufacturer should be
consulted for the proper field testing procedure if a test under design load
conditions is desired.)
If the ejector does not obtain the manufacturer's tested no-load
vacuum, the ejector should then be disassembled and internally inspected.
No-load testing is easily accomplished on a single-stage ejector system, but a
multistage ejector system must be evaluated by checking the last stage
first.
Multistage, no-load
vacuum
Typically, a multistage ejector system is started up backwards from the
last (Z) stage to the first. The Y stage cannot operate properly until the Z
stage is working, the X stage will not work unless the Y and Z are operating,
and so on.
Troubleshooting a multistage ejector system should also proceed in this
back-to-front order. Check the vacuum of each stage during process load
conditions, and compare it to its design value. When the measured vacuum of a
stage is worse than its design, the cause of the problem at that stage must be
found and corrected before proceeding any further.
The next step is to performance-test the stage in question by checking its
no-load vacuum. For example, if the stage being checked is the Y stage of a
three-stage ejector system, a blank should be installed on the Y suction flange.
Since the Y stage is designed to discharge to a vacuum created by the Z stage,
the Z stage, and intercondenser if present, must operate simultaneously during
this test.
With the Y stage steam valved off, first check and record the Z stage
no-load vacuum to be sure it is meeting the manufacturer's tested value. Then,
with the vacuum gage still connected to the Z stage, turn the Y stage steam on.
If the Z stage vacuum steadily falls off, the intercondenser is most likely the
cause of trouble and should be inspected.
As mentioned in the preliminary checklist, a condenser temperature rise much
greater or less than design may be an indication of a water-flow problem. A
water-flow problem can result in a higher condenser temperature and an
overloading of the following stage with uncondensed vapor. In this case, as the
Z stage falls off, the Y stage vacuum would follow.
Examples of direct-contact condenser problems include: a blocked tailpipe,
air leakage into tailpipe, damaged water distributor, or a plugged water nozzle.
Surface condenser problems include: a blocked drain, air leakage into tailpipe,
or split or fouled tubes.
If the Z stage vacuum is within specifications, move the vacuum gage to the
Y stage. If the Y stage vacuum measures exactly the same as that of the Z stage,
a blocked Y stage nozzle may be the cause. However, at this point, if the Y
stage vacuum does not measure reasonably close to the manufacturer's tested
no-load value, the stage should be disassembled for internal inspection.
Finding the Y and Z stage vacuums within specifications, remove the blind
flange from the Y stage suction and repeat the procedure at the X stage. It is
important to remember that each stage must meet its design vacuum before
continuing the testing.
At times it may be impractical to make and install a blind flange on the
suction connection of an ejector due to the size of the unit. In most cases,
however, these larger stages will be the W or X. If the no-load testing has
ruled out the Y and Z stages and the condensers ass possible causes of the
vacuum problem, and internal inspection of these larger stages may be the more
practical step to follow.
Internal
inspection
There are several things to look for when performing internal inspection of
an ejector. Usually any kind of corrosion or erosion that is obvious to the eye
and touch will affect the performance of an ejector. An indication of wet steam
will show as lines ("wiredrawing") etched up and down the inside of the steam
nozzle. The point along the diameter where the steam contacts the venturi is
another location that may be gouged due to wet steam.
Steam leaking around the nozzle puts an artificial load on that stage,
resulting in poor vacuum. Leakage of this sort should be noticeable as a
discoloration where the nozzle seats on the steam chest, or as erosion of the
nozzle threads. A process that causes corrosion or buildup of material on the
internals of an ejector will also effect the performance of that unit.
Critical dimensions such as the nozzle orifice or venturi bore diameter,
obtained from the manufacturer, will enable a measurement of dimensions to
determine extent of wear. Part numbers of the various ejector components should
be checked to ensure they are in the right unit. Many ejector parts, and
complete stages, are physically interchangeable and care must be taken not to
mix them.
Keep spares on
hand
At a minimum, keep at least the following components in stock:
- One steam nozzle for every single nozzle ejector stage
- One diffuser for every stage, at least in sizes through 6 in. -- higher, if
continuity of service is critical
If continuity of service is important to a process, keep a spare steam
nozzle in stock for every size ejector in the system. Spare diffusers are also
worthwhile to keep in stock, especially for smaller systems. While it is
theoretically possible for the plant engineer to recondition these parts, the
practice is not recommended because critical dimensions may be altered.
Since most nozzles are relatively inexpensive they should be considered
sacrificial; if wear is evident they may be discarded and easily replaced. A
complete Z stage should be kept in stock for important systems in critical
operations.
If these simple tips fail, don't despair. Check the nameplate and call the
manufacturer. A condition may be new to you, but chances are the manufacturer
has seen it, and corrected it, many times before. Since troubleshooting an
ejector system is quite straightforward, suppliers can usually work with you
over the phone to get the problem corrected. Experienced service people estimate
that at least 50% or more of the troubles referred to them can be solved over
the phone.
Of all vacuum-producing devices, the steam-jet ejector is the most
forgiving. Occasional inspection, replacement of parts, and adherence to design
conditions will keep it operating reliable for many years. Knowledge of these
simple procedures for avoiding trouble, and locating it if it does occur, will
save time and product in you plant.
edited by Nicholas Basta
Reprinted from CHEMICAL ENGINEERING, May 1992
|